Name of ITI :WAGHODIYA                                Position Dated :31/12/2011

Sr. No.

Key Performance Indicators

Information

Remarks

1

Total Sanctioned seats (GCVT + NCVT ) (Senior + Junior Batch including both) 

268

 

2

Total Number of Admission Forms Sold till 31st August 2011

3

 

3

Total Number of Admission Forms Returned till 31st August 2011

944

 

4

Total Number of Trainees who took Admission in Junior Batch as on 31st August 2011

201

 

5

Total Number of Trainees in Senior Batch as on 30th Jun 2011

33

 

6

Total Number of On-Roll Trainees (Junior + Senior Batches) as on End of Reporting Month.

207

 

7

Percentage utilization of student seating capacity

87%

 

8

Retention Rate (On roll * 100/ Admission) 

88%

 

9

No. of trades. (GCVT + NCVT)

7

 

10

No. of batches (GCVT + NCVT)

17

 

11

Total Number of Trainees who appeared in the Final Examination in July 2011

67

 

12

Total Number of Trainees who passed in the Final Examination in July 2011

60

 

13

Pass out percentage in August 2011

89.55%

 

14

No. of sanctioned post of teaching staff (All Trade, Maths, Drawing, Social Studies, English and others)

17

 

15

No. of currently filled posts of teaching staff (All Trades,Maths,Drawing,Social Studies,English and others)

10

 

16

No. of sanctioned posts for teaching staff (on Contract Basis - Recruitment by ITI Principal)

0

 

17

No. of currently filled posts of teaching staff (on Contract Basis - Recruitment by ITI Principal)

1

 

18

No. of  sanctioned post of non-teaching staff (including Principal)

5

 

19

No. of  currently filled posts of non-teaching staff (including Principal)

5

 

20

No. of teaching staff sent for Training (from 01 April 2011 onwards till date)

NIL

 

21

No. of Trainings attended by ITI Principal (from 01 April 2011 onwards till date)

NIL

 

22

Total Plan Budget Provision for the current financial year 2011-12

34.46

 

23

Total Plan Budget Expenditure during the current financial year 2011-12( Progressive till Date)

18.09

 

24

Total Non-Plan Budget Provision for the current financial year 2011-12

NIL

 

25

Total Non-Plan Budget Expenditure during the current financial year 2011-12 ( Progressive till Date)

NIL

 

26

Total Budget Provision (Plan + Non-Plan) for Students' Stipend in ITI during current financial year 2011-12

0.25

 

27

Total Expenditure on Students' Stipend in ITI during the current financial year 2011-12

0.05

 

28

Percentage Expenditure against Provision on Stipend during current financial year 2011-12

20.00%

 

29

Total Budget Provision (Plan + Non-Plan) for Raw Materials in ITI during current financial year 2011-12

0.80

 

30

Total Expenditure on Raw Materials in ITI during the current financial year 2011-12

0.02

 

31

Percentage Expenditure against Provision on Raw Materials during current financial year 2011-12

2.50%

 

32

Revenue Generation (if any during the current financial year)

0

 

33

Staff Utilization (Students-instructor ratio)

Full time student to all staff (including non-teaching staff)

12.0

 

Full time student to teaching staff

17.0

 

34

Short term courses conducted till date 30/09/2011 during the year 2011-12 (MES and others)

No.of Batches

2

 

No.of  persons trained

36

 

No. of trainees who have completed Motor Driving School Training.(During the Month)

NIL

 

35

No. of trainees who successfully completed and passed the CCC Course. During 2011-12

A. I.T.I Staff 

NIL

 

B. Other Government Employees 

NIL

 

36

Progress of Placement Advisory Bureau (fill up separate review form where applicable, otherwise state Not Applicable)

NO

 

37

Progress of Language Lab (fill up separate review form where applicable,otherwise state Not Applicable)

NO

 

38

No of Campus Interview held during the Year 2011-12

3

 

39

No. of Students who got jobs Year 2011-2012 (do not include figures of Apprenticeship Training )

20

 

 

No. of  Expert Faculties invited from Industries as Guest Lecturer (Attach a Separate Paper with List of Names, designation, telephone, mobile, Name of industry, complete address)

1

 

40

No. of Industrial Visits by trainees during the Year 2011-2012

4

 

41

No. of Workshops and Seminars held (from 1st April 2011 onwards)

2

 

42

No. of  IMC Meeting held             

current financial year 2011-12

3

 

Progressive (Starting from formation of IMC)

23

 

43

No.of students from Polytechnics and Engg. Colleges who came and delivered guest lecture (from 1st April 2011 onwards till date)

NIL

 